HomeTrack RecordTechno-economic and regulatory feasibility for a 20 MW / 80 MWh hybridisation
[ TRACK RECORD INDEX ]
VERIFIED RECORD
SpainLOCATION
20 MW / 80 MWhCAPACITY
2024DATE
Case ReportEVALUATE & INVEST

One Hub Energy advised

Trina Solar

Techno-economic and regulatory feasibility for a 20 MW / 80 MWh hybridisation

Energy-storage strategy for an experienced global IPP, techno-economic and regulatory feasibility of a 50 MW BESS with 5 MW PV hybridisation, plus assessment of a greenfield standalone BESS opportunity.

01
Background

An experienced global IPP with BESS projects worldwide had to define its energy storage strategy for Spain and test two very different routes: hybridising an existing PV project and a greenfield standalone BESS.

02
Process

One Hub Energy reviewed the regulatory framework and planned the hybridisation development — regulation overview, deficiencies, expected administrative and market-rule updates, and schedule and budget planning. The techno-economic assessment analysed an optimised hybridisation incorporating storage into a PV project at RTB stage, based on additional energy yield and cover against low PV capture prices, with economic feasibility and long-term valuation run on our in-house dispatch and price-taker BESS model and support on the preliminary feasibility financial model; a greenfield standalone BESS opportunity was assessed in parallel. One Hub Energy then selected the most suitable plant configuration and sizing and prepared the basic engineering documentation, including technical drawings and the documentation for the grid access update request.

03
Outcome

"Techno-economic and regulatory feasibility reports were delivered for both the hybridisation and the standalone BESS configurations in Spain."

One Hub Energy VERIFIED RECORD
Techno-economic and regulatory feasibility for a 20 MW / 80 MWh hybridisation
SPAIN
DOSSIER SPEC SHEETVERIFIED
Client EntityTrina Solar
GeographySpain
Capacity20 MW / 80 MWh
Date2024
Delivered to the client5 items
  • Regulatory review and development plan
  • Techno-economic model (dispatch + price-taker BESS)
  • Greenfield standalone BESS assessment
  • Basic engineering package
  • Grid access update dossier
Request Full Briefing

Briefings require signing a bilateral NDA for full technical metrics disclosure.

ONE HUB ENERGYonehubenergy.comCS-trina-solar-bess-hybridisation
One Hub Energy

Driving confident decisions in complex energy markets.

ONE HUB ENERGIA S.L.CIF B-01610229Parc Tecnològic Barcelona ActivaC/ Marie Curie 8-12 (Modules A201–A211) · 08042 Barcelona+34 931 215 343 · connect@onehub.energy
LinkedIn

© 2026 One Hub Energy. All rights reserved.

Backed by Octopus Energy Generation
Proyecto SNEO-20231420 subvencionado por el CDTI. Gobierno de España, Ministerio de Ciencia, Innovación y Universidades.Financiado por ENISAProyecto CPP2021-008632 financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR.

Proyecto SNEO-20231420 (OneFlex) subvencionado por el CDTI · Proyecto CPP2021-008632 (DiÓptiBa) financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR · Proyecto PR-NMN-01-2023-000444 (OneBESS) financiado por la Unión Europea — NextGenerationEU, a través del IDAE (Ministerio para la Transición Ecológica y el Reto Demográfico), en el marco del Plan de Recuperación, Transformación y Resiliencia.

We use our own and third-party cookies to improve our services, analyse traffic and personalise content. You can accept, reject or configure them at any time. Cookie policy