HomeTrack RecordDevelopment and technical advisory for the Picassent 107.91 MW / 215.824 MWh BESS, Spain
[ TRACK RECORD INDEX ]
VERIFIED RECORD
Picassent, Comunitat Valenciana, SpainLOCATION
107.91 MW / 215.824 MWh BESSCAPACITY
Development services and BESS technical advisorySCOPE
2022 (in development)DATE
Case ReportDEVELOP & BUILD

One Hub Energy advised

Sargao Energy

Development and technical advisory for the Picassent 107.91 MW / 215.824 MWh BESS, Spain

Project development plus technical consultancy — feasibility, storage sizing and regulatory review — for a 107.91 MW / 215.824 MWh battery storage project in Picassent (Comunitat Valenciana), currently in active development.

01
Background

Sargao Energy was taking a utility-scale battery storage project forward in Picassent, in the Comunitat Valenciana. A standalone BESS of this size has to be sized and justified against a regulatory framework that governs how storage connects and operates, and the administrative track runs for years before construction. The client needed both the development work and the technical basis to support it.

02
Process

One Hub Energy combined project development with technical consultancy on the same asset. The technical work covered feasibility analysis, sizing of the storage system and review of the applicable regulation for the 107.91 MW / 215.824 MWh configuration. Development ran in parallel and carried the project through its administrative milestones: admission of the administrative procedure (AA) in September 2024, environmental impact statement (DIA) in March 2025 and prior administrative authorisation (AAP) in March 2026. Technical assumptions and the permitting track were kept aligned as the project advanced.

03
Outcome

"The BESS consultancy report was delivered to Sargao Energy. This is an ongoing mandate: the project is in active development, with AA, DIA and AAP obtained to date and no closed outcome to report yet."

One Hub Energy VERIFIED RECORD
No project photo
PICASSENT, COMUNITAT VALENCIANA, SPAIN
DOSSIER SPEC SHEETVERIFIED
Client EntitySargao Energy
GeographyPicassent, Comunitat Valenciana, Spain
Capacity107.91 MW / 215.824 MWh BESS
Date2022 (in development)
Delivered to the client5 items
  • BESS technical consultancy report
  • Feasibility analysis for the Picassent storage project
  • Storage system sizing (107.91 MW / 215.824 MWh)
  • Regulatory review applicable to the storage system
  • Project development through AA, DIA and AAP administrative milestones
Request Full Briefing

Briefings require signing a bilateral NDA for full technical metrics disclosure.

ONE HUB ENERGYonehubenergy.comCS-sargao-picassent-bess-development
One Hub Energy

Driving confident decisions in complex energy markets.

ONE HUB ENERGIA S.L.CIF B-01610229Parc Tecnològic Barcelona ActivaC/ Marie Curie 8-12 (Modules A201–A211) · 08042 Barcelona+34 931 215 343 · connect@onehub.energy
LinkedIn

© 2026 One Hub Energy. All rights reserved.

Backed by Octopus Energy Generation
Proyecto SNEO-20231420 subvencionado por el CDTI. Gobierno de España, Ministerio de Ciencia, Innovación y Universidades.Financiado por ENISAProyecto CPP2021-008632 financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR.

Proyecto SNEO-20231420 (OneFlex) subvencionado por el CDTI · Proyecto CPP2021-008632 (DiÓptiBa) financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR · Proyecto PR-NMN-01-2023-000444 (OneBESS) financiado por la Unión Europea — NextGenerationEU, a través del IDAE (Ministerio para la Transición Ecológica y el Reto Demográfico), en el marco del Plan de Recuperación, Transformación y Resiliencia.

We use our own and third-party cookies to improve our services, analyse traffic and personalise content. You can accept, reject or configure them at any time. Cookie policy