Spain — portfolio, plus San Vicent del Raspeig siteLOCATION
20 MW / 80 MWh portfolio study + 10 MW / 35 MWh siteCAPACITY
Storage hybridisation pre-feasibility and BESS advisorySCOPE
2025DATE
Case ReportEVALUATE & INVEST

One Hub Energy advised

Exiom

Testing whether storage pays across a PV portfolio, then taking it to a single site

Pre-feasibility modelling of storage hybridisation for Exiom's solar portfolio, built around sensitivities on demand access permits, market participation policies and PV-BESS sizing ratios, and extended into a dedicated BESS advisory mandate for the San Vicent del Raspeig site.

01
Background

Exiom, as a developer, wanted to know whether hybridising its solar plants with storage was worth pursuing before committing development effort. The answer does not depend only on the assets: it depends on whether demand access permits are obtained, on how the battery is allowed to participate in the markets, and on the ratio chosen between PV and battery. Those variables move the economics enough that a single central case would have been of little use.

02
Process

One Hub Energy prepared a pre-feasibility study of hybridisation with storage for the portfolio of solar plants, sized at 20 MW / 80 MWh. The work covered detailed production and cost modelling and estimates of long-term revenues and returns. Rather than a single case, we built the analysis as a sensitivity framework: scenarios on demand access permits, on different market participation policies, and on different PV-BESS sizing ratios, so Exiom could see which assumptions actually drove the result. The engagement was then extended to a dedicated BESS advisory mandate on the San Vicent del Raspeig project, 10 MW / 35 MWh, applying the portfolio methodology to a specific site.

03
Outcome

"The portfolio pre-feasibility was delivered with a detailed revenue analysis and the full set of sensitivity studies on access permits, market participation policies and sizing ratios. The San Vicent del Raspeig BESS advisory mandate is ongoing at the date of this record, so no closed result is reported for it."

One Hub Energy VERIFIED RECORD
No project photo
SPAIN — PORTFOLIO, PLUS SAN VICENT DEL RASPEIG SITE
DOSSIER SPEC SHEETVERIFIED
Client EntityExiom
GeographySpain — portfolio, plus San Vicent del Raspeig site
Capacity20 MW / 80 MWh portfolio study + 10 MW / 35 MWh site
Date2025
Delivered to the client6 items
  • Pre-feasibility study of storage hybridisation for the solar plant portfolio
  • Detailed production and cost modelling
  • Long-term revenue and return estimates
  • Sensitivity analysis on demand access permit scenarios
  • Sensitivity analysis on market participation policies and PV-BESS sizing ratios
  • Site-specific BESS advisory for the San Vicent del Raspeig project (ongoing)
Request Full Briefing

Briefings require signing a bilateral NDA for full technical metrics disclosure.

ONE HUB ENERGYonehubenergy.comCS-exiom-pv-portfolio-storage-hybridisation

Where this work sits

One Hub Energy

Driving confident decisions in complex energy markets.

ONE HUB ENERGIA S.L.CIF B-01610229Parc Tecnològic Barcelona ActivaC/ Marie Curie 8-12 (Modules A201–A211) · 08042 Barcelona+34 931 215 343 · connect@onehub.energy
LinkedIn

© 2026 One Hub Energy. All rights reserved.

Backed by Octopus Energy Generation
Proyecto SNEO-20231420 subvencionado por el CDTI. Gobierno de España, Ministerio de Ciencia, Innovación y Universidades.Financiado por ENISAProyecto CPP2021-008632 financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR.

Proyecto SNEO-20231420 (OneFlex) subvencionado por el CDTI · Proyecto CPP2021-008632 (DiÓptiBa) financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR · Proyecto PR-NMN-01-2023-000444 (OneBESS) financiado por la Unión Europea — NextGenerationEU, a través del IDAE (Ministerio para la Transición Ecológica y el Reto Demográfico), en el marco del Plan de Recuperación, Transformación y Resiliencia.

We use our own and third-party cookies to improve our services, analyse traffic and personalise content. You can accept, reject or configure them at any time. Cookie policy