HomeTrack RecordAccess and connection permit updates for three PV-plus-storage hybridisations
[ TRACK RECORD INDEX ]
VERIFIED RECORD
LOCATION
3 PV-plus-storage projects, 20.2-32.76 MW each, 80.2-130.39 MWh of storage eachCAPACITY
Guarantees management and update of access and connection (A&C) permits for hybridisationSCOPE
2026DATE
Case ReportDEVELOP & BUILD

One Hub Energy advised

Confidential Client

Access and connection permit updates for three PV-plus-storage hybridisations

Guarantees management through to the correct constitution letter and processing of the access and connection permit updates for three PV plants being hybridised with battery storage, 20.2-32.76 MW each.

01
Background

Three operating-scale PV plants were to be hybridised with battery storage. Adding storage behind an existing connection point is not a design exercise alone: the access and connection permits have to be updated, and the financial guarantees associated with the new capacity have to be lodged and formally accepted before the update can proceed. Each of the three projects sat with a different grid operator counterpart, so the same process had to be run three times without letting any of them fall out of step.

02
Process

One Hub Energy took the development-services role on all three hybridisation projects. The team managed the guarantees process end to end, from constitution through to obtaining the correct constitution letter for each project. In parallel, One Hub Energy prepared and processed the update of the access and connection permits for the hybridisation of each plant, dealing with the transmission system operator on one project and with the distribution system operator on the other two. The three files were run as one workstream, with a common documentation set adapted to each counterpart's requirements, so that the storage capacity added at each site (80.2 to 130.39 MWh) was reflected consistently in the permit position.

This client does not authorise the use of its brand. The mandate is published without name, logo, photography or location: the technical scope and the scale are real and auditable, the identity is not disclosed.

03
Outcome

"The correct constitution letter for the guarantees was obtained and the access and connection permits were updated on all three projects. The three hybridisations therefore hold a permit position consistent with their PV-plus-storage configuration."

One Hub Energy VERIFIED RECORD
No project photo
DOSSIER SPEC SHEETVERIFIED
Client EntityConfidential Client
Geography
Capacity3 PV-plus-storage projects, 20.2-32.76 MW each, 80.2-130.39 MWh of storage each
Date2026
Delivered to the client5 items
  • End-to-end guarantees management for three hybridisation projects
  • Guarantees correct constitution letter obtained per project
  • Access and connection permit update files prepared and submitted
  • Processing with the transmission system operator and with the distribution system operator
  • Updated A&C permits reflecting the PV-plus-storage configuration of each plant
Request Full Briefing

Briefings require signing a bilateral NDA for full technical metrics disclosure.

ONE HUB ENERGYonehubenergy.comCS-ac-permit-updates-three-pv-hybridisations

Where this work sits

One Hub Energy

Driving confident decisions in complex energy markets.

ONE HUB ENERGIA S.L.CIF B-01610229Parc Tecnològic Barcelona ActivaC/ Marie Curie 8-12 (Modules A201–A211) · 08042 Barcelona+34 931 215 343 · connect@onehub.energy
LinkedIn

© 2026 One Hub Energy. All rights reserved.

Backed by Octopus Energy Generation
Proyecto SNEO-20231420 subvencionado por el CDTI. Gobierno de España, Ministerio de Ciencia, Innovación y Universidades.Financiado por ENISAProyecto CPP2021-008632 financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR.

Proyecto SNEO-20231420 (OneFlex) subvencionado por el CDTI · Proyecto CPP2021-008632 (DiÓptiBa) financiado por MCIN/AEI/10.13039/501100011033 y por la Unión Europea NextGenerationEU/PRTR · Proyecto PR-NMN-01-2023-000444 (OneBESS) financiado por la Unión Europea — NextGenerationEU, a través del IDAE (Ministerio para la Transición Ecológica y el Reto Demográfico), en el marco del Plan de Recuperación, Transformación y Resiliencia.

We use our own and third-party cookies to improve our services, analyse traffic and personalise content. You can accept, reject or configure them at any time. Cookie policy